Colab Building Group Pty Ltd: WorkSafe Victoria prosecution
criminal conviction28 July 2026Penalty $400K
Respondent
Colab Building Group Pty Ltd
Facts
Steel subcontractor on the Kew Recreational Centre job that outsourced fabrication of the GT1 truss to a China-based firm without having welding/QA documents verified before erection. The truss failed and part of the building collapsed in October 2022. Company now in liquidation; sentenced ex parte after a guilty finding.
Outcome
Colab Building Group Pty Ltd was convicted and fined $400,000 in the Magistrates' Court (Vic) - Melbourne (28 July 2026). Other orders: costs $7,403.
Read the source
https://www.worksafe.vic.gov.au/news/2026-07/400000-fine-after-kew-rec-centre-collapseRules Mate links to the regulator's own publication. We do not republish full decision text. Always verify the latest status against the source before acting.